We have spinklers fitted in our tower-blocks in the lobby and bin room areas.

As part of our commitment to fire safety and to provide residents with peace of mind, we also have plans to fit sprinklers in flats and throughout all the main communal areas. This is a big piece of work, so we've developed an 'infrastructure programme', which will see new and improved fire safety measures put in place in all our tower-blocks. 

This work, including the installation of sprinkers, will be taking place over a five-year plan starting in April 2019.

Estate     Blocks Start date Finish date
Boscobel     5 April 2019 June 2020
Heath Town (tower-blocks) 3 January 2020 To be confirmed
Lakefield 3 February 2020 November 2020
Heath Town (deck-access blocks) 5 April 2021 To be confirmed
Merry Hill 3 April 2020 March 2022
Stowlawn 3 January 2021 November 2021
Millfields 1 September 2021 April 2022
Whitmore Reans 2 April 2022 February 2023
Graiseley 3 March 2022 January 2023
Vauxhalls 3 January 2023 November 2023
Hickman 2 January 2023 September 2023
Chetton Green 3 September 2023 March 2024

 